26MW Self-plentiful Power Plant In Lagos Receives Revival Attention

Most of our equipment is power-driven,” he said.

Meanwhile, the Transmission Business of Nigeria (TCN), has explained outage in parts of Port Harcourt and its environs which have been free from bulk electricity deliver because Monday once members of the Nationwide Union of Electricity Employees (NUEE) stop down a key transmission line over a dispute using the guidance of Afam IV Power Station.

TCN said the disruption began on Monday, September 28, 2026, when NUEE members in Rivers Status opened the Afam to Alaoji 330kV Transmission Line 2 at the Alaoji 330kV Transmission Substation.

The organization linked the transfer to an current labour dispute betwixt the union and the orientation of Afam IV Gas Power Station.

TCN explained that the shutdown caused the 150MVA 330/132kV inter-bus transformer at Afam IV to excursion, cutting bulk electricity transmission to parts of the city and surrounding areas.

The affected facilities include the Port Harcourt Town 132kV Transmission Substation and the Elelenwo 132kV Transmission Substation. It added that restoration will happen as before extended as conditions authorize protected reconnection.

TCN apologised to electricity consumers in the affected areas for the inconvenience and promised to preserve the community updated as the declare develops.

The 26 Megawatts Akute Power Plant in Lagos is receiving attention, which is expected to upgrade electricity provide in the Status.

Fenchurch Crew announced plans to rebuild the power station and furnish dedicated electricity to primary Lagos waterworks, alongside the initial 10MW expected before the complete of four months.

The project, being developed by Fenchurch Power Unchanging across Aggregate Utilities Tight, the collection’s special cause vehicle, is being delivered under a concession agreement alongside the Lagos Condition government.

The remaining 16MW is expected to be delivered in 12 months, whilst surplus power will be exported to the Ikeja Electric Network.

The project is expected to support the operation of the Akute intake, as well as the Iju and Adiyan waterworks, whose equipment depends heavily on electricity for water production.

Speaking during a stakeholder tour to the Oregun fabrication yard of Jubaili Bros, where equipment for the project was being planned, collection principal executive officer of Fenchurch Fixed, Olufemi Bakare, said the project was intended to preserve the water infrastructure running reliably.

”Water needs power. The 60MVA 132/33kV transformer at the Port Harcourt Mains 132kV Transmission Substation was furthermore affected.

The business said it is current including appropriate stakeholders, including the Nigerian Self-enough Platform Administrator (NISO), to bring the affected facilities assist virtual. Lagos Declare has invested significantly in its water infrastructure, and our mandate is to hold it running reliably round the clock,” he said.

Leader of Production, Lagos Water Corporation, Agiri Mustafa, said consistent electricity was important to water production as most of the corporation’s equipment was power-driven.

He said the corporation would be the principal off-taker of the electricity when the equipment was installed. ‎”Power is a highly important element of water production commonly.

Source: 26MW Independent Power Plant In Lagos Receives Revival Attention

Terfa Ukende

Terfa Ukende is a Nigerian travel writer, blogger, and the founder of Watch Nigeria. Combining an analytical background in Computer Science and Statistics from Joseph Sarwuan Tarka University, Makurdi (JOSTUM) with years of on-the-ground fieldwork, Terfa has crossed dozens of Nigerian cities—from Kano and Yola to Lagos and Port Harcourt. He founded Watch Nigeria to counter regurgitated travel advice with firsthand, independently verified reporting on routes, accommodations, and local culture. When not on the road, he is planning his next cross-country expedition.